Staining pt 2

The ceiling needed staining. In total near 250^m and three layers. It took about 12(?) cans. Staining-sanding-staining-sanding-staining. Pfffft…

shop display of staining procucts
A person needs choices
A few cans of paint and wood restoration materials
The first haul from the shop
Wooden attic, ready to be stained
All set
Freshly stained, still wet caeiling
Ceiling left to dry

Putting in the ceiling

The ceiling underneath the rafters (hanebalken) is about done. the end still need to be done in order to be connected properly to the roof there. But the main thing is ready.

First everything had to be leveled as the rafters were not really at the same height. So with underlayment, a spitit level and some thread the base was laid out. Then laths were fixed to that structure so that finally the underlayment panels could be fixed to them.

spirit level
spirit level
Leveling the base of a ceiling
Leveling the base of the ceiling
Leveling the base of a ceiling
Leveling the base of the ceiling
Leveling the base of a ceiling done
Leveling the base of the ceiling done
setting up laths of a ceiling
setting up laths of the ceiling
Underlayment panels as a ceiling
The start is there
Ceiling made of underlayment
Ceiling nearly done

Pouring the floor

The floor needs a finish too before moving in. The cement floor will get another type of cement finish (egaline) and then some coating layers. Actually this is more meant as a base layer for wooden floors, but everyone seems to like it enough so that the wood is left out of the process…

In order to let the stuff not leak into the isolation, some gaps had to be closed first.

bumper tape gap
bumper tape gap left between floor and original structure
bumper tape gap between floor and original structure closed
bumper tape gap between floor and original structure closed
Floor without finishing layer
Floor without finishing layer
Floor with wet finishing layer
Floor with wet finishing layer
Floor with drying finishing layer
Floor with drying finishing layer
Floor with dry finishing layer
Floor with dry finishing layer

Plastering

In order to be able to move into part of the house, that part was plastered asap. Also something you wanna leave up to the expert I guess

foil to protect tiles from plastering
tiles protected from falling plaster
primed walls before plastering
primed walls before the plastering
half plastered corner
half plastered corner
plastered walls
plastered walls
freshly plastered walls
plastering done

Heating

The heating is installed! The boiler connected to all the underfloor heating below and above to the chimneys. Next to that all the other water and air related things were connected.

underfloor heating plan
underfloor heating plan
Boiler
Boiler
Hole in the roof
Hole in the roof
Hole in the roof
Hole in the roof
Chimneys placed
Chimneys placed

Shower – step 2

The shower is taking shape. Tiles chosen, purchased and placed. The latter not by us. Let’s leave that up to the expert.

wall tile on floor tile
Trying to see if the floor and wall tiles match
Sealed limestone floor tiles
New floor tiles have arrived
close-up of tiles. Wall and floor
Testing the combination of the tiles in the shower
picture of newly tiled shower room
Do not walk on newly tiled floor

Closing the gaps

The paneling of the ceiling left some gaps in the original beams/trusses. Time to close the gap. Some jigsaw action!

Open gap under old farmhouse trus
Open gap in the paneling under original truss
Closed gap in the paneling under original truss
Closed gap in the paneling under original truss

Doors

The doors have been made to fit and have their hinges etc. Looks homely but still need ‘some’ sanding.

Lets just say the pictures’ quality is reflecting the work still needing to be done…

first doors in the frame
first doors in the frame

sneak peak of the bathroom

The bathroom is being tiled. First the walls and then the floor (for which we still need to find the proper tiles. Preferable 1.5cm thick and no bigger than 45x45cm. The black tiles in the ‘test setting’ do not meet those technical requirements…

sneak peak of the bathroom (half tiled)
sneak peak of the bathroom
testing tile combinations
tile combinations lab